Qatar Operations Offices

Doha, Qatar

Scope

To supply and install 8 office buildings for operation of critical national.

Client

Consolidated Contractors Corporation

location

Doha, Qatar

Key Challenges:

  • Timeframe – all buildings to be installed and ready for use within 2 months of arrival on site
  • Large and unfamiliar workforce tasked with installing the buildings locally
  • Strict local code to be adhered to for MEP while also coming under budget

Our Approach:

  •  Designed economical, smart office spaces to fit the client’s brief
  • Arranged for an LC to facilitate the client’s desired payment terms
  •  Shipped all the bundles and containers to Doha under CIF terms
  • Arranged manufacture of custom-made open balconies with glass balustrades
  • Designed and installed unique flashing and parapets
  • Sent a team to supervise 70+ local assembly/construction workers

OutCome:

  • All buildings were supplied on time and within budget
  • The operations offices were completed on schedule, allowing a major piece of national infrastructure to open as planned